Phase III of Technopark to get ready by 2013Illustrative image – not actual.

The Phase III of expansion at Technopark in Thiruananthpuram is epected to be completed early 2013.

The Phase III with an investment of Rs 292 crore is coming up on 333 acre with the built-up area to 7.1 million sq.ft. Allotment of space has already been started and nearly 40 companies have taken up space in the new facility. Of which some of the companies are HCL, Oracle and CapGemini.

Currently, work on the modern twin-tower coming over one million is complete. Finishing touches being applied to the approach road and surrounding area are progressing at a fast pace. A 110 KV substation has already been commissioned on the campus. One floor each in the two towers spread over 92 acre designated as SEZ is being developed as smart business centre at a cost of Rs three crore.

Related Links:
Project profile

← All latest storiesBack to top →