Illustrative image – not actual.The Madhya Pradesh Power Generating Company (MPPGCL) is likely to begin work on the Phase II of Singaji thermal power project in Khandwa district once environmental clearances have been received. The Phase II comprises of two units of 660 MW each and is to cost Rs 6,500 crore.
The first phase of 2x600 MW capacity is expected to be completed by 2012. The total land requirement of the project is 1,232 ha of which 1,163 ha have already been acquired. Phase I entails a cost of Rs 6,750 crore. Of the total, Rs 5,200 crore debt portion will be obtained from various banks and financial institutions. The state government will contribute the rest 20 per cent (Rs 1,300 crore) as share capital.