Illustrative image – not actual.Power Grid Corporation of India (PGCIL) is likely to commission the phase II of its Rs.3,365.61 crore Talcher-Kolar high voltage direct current (HVDC) bi-pole project by November or early December 2002. The project is expected to be fully operational by March 2003. The first phase of the project was commissioned on September 15, 2002.
The east-south interconnector project would enable the evacuation of 2,000 MW from National Thermal Power Corporation’s (NTPC) Talcher II (4 X 500 MW) super thermal power project in Orissa to the power deficient states in the south - Andhra Pradesh, Karnataka, Kerala, Tamil Nadu, and Pondicherry.
The power would first go to Kolar near Bangalore where Direct Current (DC) would be converted to Alternate Current (AC). Through extra high voltage (EHV) AC lines, the power then would be dispensed to the southern states.