Illustrative image – not actual.PowerGrid Corporation of India’s (PGCIL) second phase of the national power grid will reportedly be commissioned in the first week of December 2002. Earlier, the corporation had scheduled the date to December 2003, which later was revised to August 2002.
The 450-km Raipur-Rourkela AC system will transmit 800-1,000 MW from the eastern regions to western India, which has a peak hour shortage of more than 5,000 MW. The Rs.400 crore project is expected to alleviate the acute power shortage situation currently existing in Maharashtra, Gujarat, Madhya Pradesh and Goa.
PGCIL has planned projects worth Rs 71,000 crore in the 10th and 11th Five Year plans. A sum Rs 51,000 crore would be invested through PGCIL's internal resources while the rest would come through private participation.