Phase-II of Mango water project to start in SeptIllustrative image – not actual.

The ground work for the second phase of the Mango drinking water project in Jamshedpur has been completed and the construction process will start from September 2016. In the second phase, 16,000 connections will be given, and in next six months water supply will start.

The Jharkhand government has already sanctioned Rs 35 crore for laying pipelines in the left out areas of Mango in the second phase.

The first phase of the project has been completed at a cost of Rs 64.18 crore, while around two sq km radius of areas which came up after the DPR of the first phase was completed, has been left out of the water project.

The Mango project — aiming to supply 48 million ltr per day — started in 2005 as a public-private partnership between the state drinking water and sanitation department and Tata Steel subsidiary Jusco.