Illustrative image – not actual.Commissioning of Phase-II of the Kochi LNG terminal of Petronet LNG at Puthuvype is likely to be delayed due to the time lag in laying the pipeline in Kochi-Bangalore, and Kochi-Mangalore segments.
Work on the pipeline is moving very slowly. Of the total 900 km lines passing through Kerala, Karnataka and Tamil Nadu, only 30 km has been completed so far. Around 505 km of the pipeline passes through Kerala, 310 km through Tamil Nadu and 85 km through Karnataka.
The Tamil Nadu government is also opposing land acquisition and the issue is now under judicial scrutiny. Once the matter gets sorted out, the pipeline work will be completed within 6-7 months.
The company has now decided to take a cautious approach in bringing in LNG from overseas suppliers, as marketing and distribution are a major concern.
Work on the Rs 4,200 crore terminal in the southern end of Vypin island was completed in December 2012, though Petronet LNG had originally planned to commission it in March 2013. For various reasons this was postponed to June 2013, but not realized.