Illustrative image – not actual.GVK Industries plans to completely debt-fund the second phase of its Jegurupadu gas based power project, in East Godavari, Andhra Pradesh. The 220 MW expansion project is estimated to cost Rs.750 crore. The tariff would be maintained at around Rs.2.65 i.e. a fixed component of 93 paise and fuel cost of Rs.1.72 per Kwh.
Industrial Development Bank of India (IDBI) has been
appointed as the lead arranger for funds. IDBI has agreed to underwrite the entire
debt raised due to the proposed low tariff.
The 235 MW first phase, of the Jegurupadu power project, has an equity component of Rs.195 crore. This equity is held by the following:
|
Company |
Equity (%) |
|
GVK
Industries |
50 |
|
CMS
Generation Corpn, US |
23 |
|
IFC
Washington |
10 |
|
AP
Transco |
2 |
|
Financial
Institutions |
14 |