Phase-II of Dabhol power project to incur $92 million cost overrunIllustrative image – not actual.

Phase-II of the Dabhol power project is expected to incur a cost overrun of $92 million. This follows settlement with LNG contractors of their claims for contract variations and geo-technical problems. The cost overrun will be financed through the project completion support from the shareholders.

 

The phase-II of the project is likely to be commissioned in mid-2001. It is estimated to cost $1,868 million. This is expected to be financed as follows: equity ($454 million), bank  loan ($497 million), OPIC loan ($60 million), JExim Bank ($258 million), OND loan ($90 million), MITI loan ($176 million), NLDs ($235 million) and rupee loan ($98 million).