Illustrative image – not actual.Work on the Phase II of the high foamed coaxial cables unit being set up by Leading Solution Cable India, is expected to be completed by November 2011.
The project is being set up in six phases at Sector 5, Bawal in Rewari district of Haryana. Spread over 40 acre, it will have a capacity of 83 lakh meters per annum. The company is pumping in Rs 500 crore in setting up the project.
Taein Construction Company, Korea, is the civil contractor for the project while Austria based Rosenda is the machinery supplier.