Illustrative image – not actual.Essar Oil is likely to commission the Phase-I of its Rs.10,000 crore, 10.5 million tpa Vadinar refinery in Gujarat by July 2006. In the first phase, the 6 million tpa mother unit will be commissioned.
The Phase-I will produce motor spirit or petrol and diesel from its mother unit. This will help the company to rejuvenate its retail network of more than 500 pumps across the country.
The commissioning of the mother unit, Essar will have its retail network back in business by end of July 2006. Work on the entire project is scheduled for completion by April 2007.
The power plant or the utility plant with 77 MW capacity will be the first unit to be commissioned in the complex in February 2006.
Essar has simultaneously started work on the crude pipeline and jetty, which will soon receive its first crude consignment for the refinery. The tank farm for crude and finished products is also on the verge of completion and is undergoing hydro-testing.
The company also plans to commission 1,500 to 1,800 outlets by the end of 2006 and 5,000 retail outlets by 2008.
Also see:
Vadinar refinery expected to be operational by June 2006 (08-Jul-05)