Phase I of ONGC's Mumbai High platform project completeIllustrative image – not actual.

ONGC has informed that Phase I of the 9-well platform project, of its Mumbai High Asset, has been completed successfully before its schedule of April 15.

This is a part of the ONGC's redevelopment plan - to enhance production - from the Mumbai High (South) field of ONGC.

The project, to be completed in two phases, was awarded to Larsen & Toubro on February 20, 2004 at a cost of Rs.514.19 crore plus 84.31 million euro (total Rs 1,006.50 crore).

Under Phase II, four well platforms - RS4 (6 slots), RS5 (9 slots), RS7 (9 slots) and RS8 (6 slots) - will be installed and are expected to be completed by February 28, 2006.