Illustrative image – not actual.Work on Phase I of the one million tpa cement unit being set up by Lalitha Cements is underway with 25 per cent of the construction work completed.
The Rs 341 crore project located at Mattampally in Nalgonda district of Andhra Pradesh also comprises a 15 MW coal based power unit.
PR Raj & Associates, Hyderabad, is the civil contractor for the project. Meanwhile, FCB, France, and Anexco, Delhi, will supply machinery for the project which is slated to be completed by December 2010.
On the other hand, the company proposes to set up a one million tpa cement unit along with a 10 MW cola based power unit in Phase II. The company hopes to mop up funds for the Rs 259 crore project by mid-2010.
prjexcl