Illustrative image – not actual.Maharashtra Tourism Development Corporation (MTDC) has completed the first phase of restoration work of Ajanta and Ellora caves at a cost of Rs.98 crore.
MTDC now proposes to undertake the second phase with an investment of Rs.500 crore. However, the proposal has not yet been finalised.
Out of the proposed Rs.500 crore investment, 82 per cent would be funded by Japan Bank for International Cooperation, while the remaining 18 per cent would be funded by the Maharashtra state government. The investment would be in a phased manner. This phase is expected to be completed within 5 years.
MTDC also plans to set up a tourist reception centre 4
kms away from the caves. It has also been proposed that tourist buses and cars would
not be allowed beyond this centre and tourists would have to travel to the
caves in eco-friendly electric buses.