Illustrative image – not actual.L&T and Malaysia's Scomi Group are expected to commission the Phase I of Mumbai Monorail by end-2010.
The project which is an initiative of the MMRDA is being executed at an outlay of Rs 2,460 crore.
The project involves design, construction, installation, testing and commissioning from Wadala to Chembur via Mahul (approx 9 km) in Phase I and Gadge Maharaj Chowk to Wadala (approx 11 km) in Phase II. The second phase is likely to be completed by December 2011.
The two routes will have 15 sets of four-car trains plying at stations after every four minutes. Coaches for the monorail are being manufactured at Rawang near Kuala Lumpur in Malaysia and shipped to India.