Phase I LNG pipeline at Kochi nearing completionIllustrative image – not actual.

The final work of Phase I of the LNG pipeline at Kochi is likely to begin on 15 November 2010.

The final work involves laying of pipes from Vypeen to Aluva connecting the major industries in Kochi. The work is being undertaken by GAIL (India).

In the first phase, a 94-km long pipeline, involving a cost of over Rs 260 crore will be laid from Kochi to Aluva. The main pipeline will have feeder lines to Vypeen, Udyogamandal, Kalamassery and Kakkanad. Phase I is slated to be completed by May 2011.

GAIL has almost completed the construction of the receiving, storage and re-gasification terminals at Kochi. The terminal will have the capacity of 2.5 million tpa. Phase I is slated to be completed by May 2011.