Illustrative image – not actual.Cairn India is all set to commission its 590-km crude oil pipeline, from its Barmer field in Rajasthan to near the Gujarat coast, early-July 2010.
The pipeline is likely to help reduce the total cost of production and transportation (trucking and shipment) from the present $10-12 per barrel to $5-6 per barrel.
The company plans to lay the Phase II 80 km pipeline to Bhogat (Jamnagar, Gujarat) after commissioning of the first phase.
Cairn has invested around $1 billion (Rs 4,500 crore) in laying the 670-km pipeline from Barmer to Bhogat to transport crude oil to the refiners like Indian Oil Corporation, Reliance Industries and Essar Oil.