Phase 3 and 4 of Tarapur nuclear power plant to be completed by 2004Illustrative image – not actual.

Phase 3 and 4 of the Tarapur nuclear power plant in Thane district of Maharashtra are likely to be completed by 2004. Each plant has a generation capacity of 500 Mwe.

 

The Union minister for petroleum and natural gas, Mr.Ram Naik has held discussions with the Maharashtra chief minister Mr.Vilasrao Deshmukh, to consider the problem of rehabilitation of the persons displaced on account of the project.

The project has been delayed inordinately by about 6 years primarily due to problems related to land acquisition and rehabilitation of the persons affected by the project. Consequently, the project cost has escalated from the originally approved Rs.2,427.51 crore to about Rs.8,949 crore.

Phase 1 and 2 of the plant have a capacity of 220 Mwe each.