Illustrative image – not actual.Phase 3 and 4 of the Tarapur nuclear power plant in Thane
district of Maharashtra are likely to be completed by 2004. Each plant has a
generation capacity of 500 Mwe.
The Union minister for petroleum and natural gas, Mr.Ram
Naik has held discussions with the Maharashtra chief minister Mr.Vilasrao
Deshmukh, to consider the problem of rehabilitation of the persons displaced on
account of the project.
The project
has been delayed inordinately by about 6 years primarily due to problems
related to land acquisition and rehabilitation of the persons affected by the project.
Consequently, the project cost has escalated from the originally approved
Rs.2,427.51 crore to about Rs.8,949 crore.
Phase 1 and 2 of the plant have a capacity of 220 Mwe each.