Illustrative image – not actual.Power Grid Corporation of India’s transmission system
connecting the eastern region to the southern region, is likely to cost Rs.600
crore more. This project,
which would be completed in August 2002, is likely to cost more as the project
may become ineligible for some duty and interest rate concessions as was
conceived in the original project plan.
It may be mentioned that, as per the original plan, part of the project cost was to be met by a World Bank loan of $475 million, which was sanctioned in May 1998. Accordingly, the Centre then, accorded a deemed export status, on the condition that if the World Bank loan did not come through, then PGCIL would have to pay the Government back the revenue benefits it had got in the interim period.
Subsequently, however, with the sanctions imposed on
India after the nuclear tests, all World Bank loans were frozen. Thus, PGCIL is
now faced with the consequences of not only coughing up Rs.600 crore, waived as
part of the customs duty payment, but also a penalty of 24 per cent interest.
