Illustrative image – not actual.Power Grid Corporation India Ltd (PGCIL) would be
signing a joint venture agreement with Tata Power Company (TPC), for the 400 kv
transmission line project associated with the 1,020 MW Tala Hydro Electric
Power Project in Bhutan, today - 1 February 2002.
PGCIL would hold 49 per cent equity in the project,
while the Tatas would hold 51 per cent equity with an investment of Rs.400
crore in this project. The project is estimated to cost Rs.1,100 crore.
The project, to be implemented with a debt-equity
ratio of 7:3, is expected to be commissioned by 2004 - 05.