Illustrative image – not actual.PGCIL is likely to set up a stop gap evacuation facility for 800 MW Unit I of Tata Power's ultra mega power project (UMPP) in Mundra, Gujarat.
PGCIL proposes to set up the 400-kV three double circuit transmission lines in Patan district to evacuate power from the Tata UMPP. The three transmission lines are between Mundra-Vadavi, Mundra-Limadi and Mundra-Jetpur.
It has sought an additional forest land of 29.383 ha. However, it is yet to get final forest clearance as well as right of way to set up the transmission link to evacuate power from the 4,000-MW UMPP, slated to be commissioned in September 2011. Part of the transmission link passes through the Wild Ass Sanctuary in Kachchh district. The company proposes to utilise part of an existing line (Mundra-Limbdi and Bachau sub-station) to evacuate power till the time it gets final regulatory approval.