PGCIL, Tata to sign pact for Tala project soonIllustrative image – not actual.

Power Grid Corporation of India Ltd (PGCIL) and Tata Power are likely to sign the agreement for the transmission lines, associated with Tala Hydro Electric power project in Bhutan, on 25 January 2002.

 

The Tatas would hold a majority stake of 51 per cent in the project, while the remaining would be held by PGCIL with an investment of Rs.148 crore.

 

The transmission project is estimated to cost Rs.1,200 crore.

 

The project envisages 400 kV transmission lines carrying power from the power project in Bhutan to Delhi, crossing the northeastern, eastern and northern regions of India.

 

Related News:

 

Tata Power bags Tala transmission project