PGCIL signs MoUs for transmission projectsIllustrative image – not actual.

Power Grid Corporation of India, on 23 March 2006, signed MoUs with five power project promoters to jointly develop transmission facilities associated with their power projects.

The respective joint ventures between the power producers and PGCIL will together develop 5,000 circuit km of transmission lines and six new sub-stations with a total investment of Rs.5,300 crore. The project would also involve upgrading five existing sub-stations.

PGCIL will have a minority stake of 26 per cent in the respective joint ventures. The remaining 74 per cent  stake and management control will rest with the power producer. The projects are likely to be executed on a 70:30 debt-equity ratio. The total equity component of all the projects works out to Rs.1,590 crore out of which PGCIL will contribute Rs.413 crore (for a 26 per cent stake).

The five power producers are ONGC/IL&FS, Essar Power, Torrent Power, Jaiprakash Group and Teesta Urja. These companies are together setting up projects with aggregate capacity 5,900 MW.

Promoter Power Project Fuel State Capacity (MW) Cost of transmission project (Rs.crore)
ONGC/IL&FS Tripura* Gas (CC) Tripura 1,100 2,000
Teesta Urja Teesta Hydro Sikkim 1,200 1,500
Jaiprakash Associates Karcham Wangtoo Hydro Himachal Pradesh 1,000 750
Essar Power Hazira Gas Gujarat 1,500 800
Torrent Power Surat Gas (CC) Gujarat 1,100 250
Total for five projects 5,900 5,300
Total equity component of all five projects [70:30 debt equity] (Rs.crore)   1,590
Out of which equity contribution of PGCIL [26 per cent]  (Rs.crore)   413
*Power project might be implemented by ONGC alone (click here)

While ONGC/IL&FS is developing a 1,100 MW gas-fired plant at Tripura, while Essar and Torrent are setting up projects with respective capacities 1,500 MW and 1,000 MW in Gujarat. Jaiprakash Group is implementing the 1,000 Karcham Wangtoo project in Himachal Pradesh while Teesta Urja is developing the 1,200 MW Teesta project in Sikkim.

India's power transmission sector is estimated to need Rs.71,000 crore of investment till 2012. A national grid supporting 30,000 MW of power capacity has been envisaged, which PGCIL will develop through the public-private partnership mode.

It may be noted that while PGCIL has signed these five MoUs, the final agreement with Reliance Energy for a similar joint venture is pending finalization. The two companies were supposed to develop a joint venture for power evacuation associated with the Koldam power project and Parbati power project in Himachal Pradesh. The formal MoU, which was to be signed on 16 January 2006, is still pending. (more news..)

 