PFC to complete EIA report for captive port by April 2011Illustrative image – not actual.

PFC is likely to complete the comprehensive three-season environment impact study (EIA) report for the Panaiyyur captive port in Tamil Nadu by April 2011.

The completion of the EIA study report will help in the implementation of the 4,000 MW Cheyyur ultra mega power project (UMPP) in Tamil Nadu. The Union MoEF is likely to give final nod for the project only after the EIA reports for, both, the port and the power project, are put up together for approval.

PFC has already completed a preliminary one-season EIA-study for the port, as well as the mandatory three-season study of the power project. It has awarded the ocean related studies, marine EIA and port feasibility to National Institute of Ocean Technology.

The Tamil Nadu Maritime Board has already given its 'in-principle no objection clearance' for use of sea water by the UMPP and port developer. PFC has applied for the acquisition of land for the port to the state government.