Illustrative image – not actual.Power Finance Corporation (PFC) has deferred the deadline for submitting requests for qualification (RFQs) for the 4,000 MW Tilaya Ultra Mega Power project in Jharkhand to10 April 2007 from 20 March 2007.
According to the original plan, PFC had asked bidders to submit RFQs by 20 March 2007, while their short-listing based on responses to RFQs and issuance of request for proposal (RFP), were to have taken place on 2 April 2007. But now, the whole schedule has been revised. PFC proposes to shortlist bidders and issue letters of intent before 16 July 2007 and subsequently sign agreements before 17 September 2007.
The development of the Tilaya project includes establishment, operation and maintenance of a 4,000 MW coal-fired pit head power project. This will include mine development and transportation of coal from the proposed allocated captive coal mines at North Karanpura.
Also See:
ultramega5