Illustrative image – not actual.In September 2001, Power Finance Corporation (PFC) committed to extend a loan of Rs.1,000 crore to Neyveli Lignite Corporation (NLC) for the expansion of its Mine-II and Thermal Power Station TPS-II.
The expansion of Mine-II entails an
increase in capacity from 10.5 to 15 million tonnes per annum. The capacity of
TPS-II is proposed to be raised by 500 MW to 1970 MW. The projects are expected
to be completed by the end of the Tenth Plan period. The projects received CCEA approval in
June 2001.
Details of project financing are as
follows:
|
|
Mine-II
|
TPS-II
|
|
Equity |
674.52 |
671.38 |
|
Foreign
currency loan |
489.05 |
131.63 |
|
Domestic
borrowings |
857.89 |
1213.08 |
Total
|
2021.46 |
2016.09 |
|
(All
figures are in Rs.crore) |
||
Meanwhile, the expansion of TPS-I
is nearing completion. The first 210 MW unit is expected to produce power by
January 2002. The second 210 MW unit may commence generation by May 2002. These
two units, part of the Rs.1,420 crore TPS-I expansion, would increase the
installed capacity of TPS-I to 1,020 MW. This would take NLC’s total installed
capacity to 2,490 MW.
Work on the feasibility report for Mine-III
and TPS-III, has begun. This project entails lignite production of
eight million tonnes and a 1,000 MW power plant, and is likely to cost
Rs.11,000 crore.