Illustrative image – not actual.Petronet LNG is expected to open the bids for the engineering, procurement and construction (EPC) contract for setting up the 2.5 million tpa liquefied natural gas (LNG) terminal project at Kochi in Kerala on 30 April 2007.
The pre-bid meeting has taken place and three companies viz, a Consortium of IHI (Japan), Technigas and Sofra Gas both from France were in the fray. After evaluating the bids, contract will be awarded before 30 June 2007.
Since the supply of LNG by Gorgan will begin only by 2012, PLL is currently negotiating with Ras Gas, Qatar and an Algerian firm to ensure supply for the Kochi terminal scheduled for commissioning by mid-2010. The Qatari company, which is supplying 7.5 million tpa to Dahej, has agreed to supply 1.5 million tpa and a similar volume will be available from Algeria.