Petronet to finalize EPC contractor on 26 MayIllustrative image – not actual.

Petronet LNG will finalize the EPC contractor for the proposed 2.5 million tpa Kochi LNG terminal on 24 May 2005. It is learnt that four foreign companies, all of whom have an Indian partner, have been shortlisted for the project. (Names of the shortlisted bidders are not yet available.)

US-based Flour Daniel, which had conducted the total feasibility study for the project has submitted its draft report which has been approved by Petronet. It has also completed the risk analysis and the final report would be submitted to the Union Ministry of Environment and Forests for clearance.

Petronet is now looking for another party to prepare the tender documents for the project. Besides, it would be selecting a company for preparing the design. All these process would be over by December 2005 and physical project work is likely to start by January 2006.

Also See:

Petronet's Kochi LNG terminal: Work to begin in Jan 2006 (09-May-05)

← All latest storiesBack to top →