Illustrative image – not actual.The Union government has reportedly asked Petronet LNG to complete the unfinished 5 million tpa LNG terminal of Dabhol Power Company. This is a move to make the project "attractive" to a new buyer.
PLL has estimated that it would take $100 million (approx Rs.450 crore) to complete the unfinished LNG terminal. PLL has also suggested that the terminal could function with three storage tanks as against the originally planned five. It may be mentioned that the original design had five storage tanks out of which two have been constructed and the third is lying undone. It is not clear how much would be the reduction in handling capacity if two tanks are dispensed with. Assuming that the five tanks are identical, the revised storage capacity would work out to 3 million tpa of LNG (or 12 mmscmd of gas).
Enron's 2,184 MW plant would require an estimated 2.73 million tpa of LNG (or 10.92 mmscmd of gas). The additional storage capacity was intended for trade.
It is understood that the power plant and the LNG terminal would be auctioned separately. PLL has expressed its interest in acquiring the terminal, once it is up for sale.