Petronet CCK successfully completed trial runs on its Kochi-Coimbatore-Karur pipeline project on 31 March 2002. The pipelines have a capacity of 3.3 million tonnes and would carry petroleum products such as petrol, diesel and kerosene.

 

The pipelines are provided with turbine and density metres and temperature measuring sensors; and the readings from these will be monitored from a control room. The first tap-off point is located on a 92-acre premise at Irugur (12 km from Coimbatore). The premises houses 10 floating roof tanks, two cone roof tanks for slop and two cone roof tanks for storing water. The gross storage capacity of the terminal is 1,14,500 kilo-litres. The last terminal at Karur also houses 10 floating roof tanks and four cone roof tanks with a total storage capacity is approximately 1,36,000 kilo-litres. The Karur terminal will cater to the requirements of Karur, Dindigul, parts of Erode, Namakkal and Tiruchirappally in Tamil Nadu.

 

The project was delayed by one year due to heavy monsoon in Kerala and problems in land acquisitions. However, the project reported no cost overrun.

← All latest storiesBack to top →