Illustrative image – not actual.Petronet LNG Ltd is considering doubling the capacity of its liquefied natural gas (LNG) terminal at Dahej in Gujarat, from 5 to 10 million tonnes per annum, following expectations of a huge future demand for LNG.
The capacity expansion plans would be finalised when the terminal nears completion. The expansion would entail construction of an additional storage tank at a cost of $70 million.
According to Mr Suresh Mathur, Chief Executive Officer and Managing Director of Petronet LNG, work on the project is progressing as per schedule and cost. Around 2,000 people have been mobilised for the construction of the jetty and storage tanks.
Meanwhile, Petronet is also planning to set up a 2.5 million tonne LNG terminal at Kochi in Kerala.