Illustrative image – not actual.With this, it would take its capacity to 17.5 million tonne, including the five million tpa that is in progress. The company expects to complete at least 50 per cent of the current expansion by June and the remaining by November 2016.
At present, the joint venture company between Gail, ONGC, IOC and BPCL is moving ahead with the expansion of 15 million tonne from the existing 10 million tonne. The expansion is expected to be completed by November 2016.
The company is simultaneously working on its Kochi terminal which completed its first full year of operations in March. To reduce the impact of lower volumes at the Kochi terminal, Petronet LNG imported an LNG cargo and re-loaded for exports. It also performed gas-up and cool-down services for a warm LNG vessel and provided bunker fuel to a vessel.
The work on the pipeline in Kerala is now going to take place soon. Once all the approvals are in place it would not take more than six to eight months for laying the pipeline.