Illustrative image – not actual.On 28 June 2002, Petronet
Central India (PCIL) issued revised final bids to the 3 pre-qualified
companies, viz. the Reliance group, Larsen & Toubro and the Moscow-based
Sun Group of Khemkas. These companies have been asked to submit their final
technical and financial bids in September 2002.
It may be recalled that in February 2002, PCIL had invited final bids from the 3 pre-qualified companies. However, there the bidding process was delayed, which has led to the issue of revised bids.
The project envisages the setting up of a 1,760 km
pipeline that would start from Jamnagar (Gujarat) and go up to Ratlam in
Rajasthan, passing through Rajkot and Koyali (both in Gujarat), en route. From
Ratlam, the pipeline would fork -- one branch would extend to Kota in Rajasthan
and other would come south to Itarsi in Madhya Pradesh.
It may be mentioned that the bidding process of the
project has been delayed, which is likely to push the completion of the project
beyond December 2003, the proposed completion date.