PEDA to set up 10 MW biomass project in PunjabIllustrative image – not actual.

Punjab Energy Development Agency plans to set up a 10 MW biomass based power unit at Fazilka in Ferozepur district of Punjab. Meenakshi Group has been appointed as the consultant and civil contractor for the project.

At present, the company is awaiting necessary approvals and clearances for the project. The detailed project report is approved and work on the project is likely to begin by May 2008. The proposed project to cost Rs.40 crore is scheduled for completion by 2010.

PEDA is also setting up a 31 MW biomass based power unit at Sunam in Ferozepur district, works for which is expected to commence by June 2008.