Pathankot Mandi Highway, a wholly-owned subsidiary of the IRB Infrastructure Developers, has achieved financial closure for a road project.
The scope of work includes rehabilitation and upgradation to four-lane configuration and strengthening of Punjab/Himachal Pradesh Border to Mo from 11.000 km to 42.000 km (design length - 28.700 km) of NH-20 (New NH-154) of Pathankot-Mandi Section in the state of Himachal Pradesh on hybrid annuity mode (HAM) (Package-IA).
The company’s bid cost is Rs 828 crore. The construction period of 730 days and operation period of 15 years commencing from COD.
The project involves a grant of Rs 331 crore from NHAI, equity of Rs 124 crore from the company and project financing of Rs 373 crore from the lenders.