Patel Engineering emerges as L1-bidder for construction of Renukaji Dam in Himachal PradeshIllustrative image – not actual.

Patel Engineering has been declared the lowest bidder (L1) by Himachal Pradesh Power Corporation (HPPCL) for the construction of the Renukaji Dam Project (Package 1).

The contract valued at Rs 910.08 crore includes the construction of three diversion tunnels with diameters of 9.5 mtrs. and lengths of 1,379  mtrss, 1,468  mtr.s, and 1,590 mtrs. It also covers the development of three inlet and outlet portals for the tunnels, along with six km of access roads. As part of the project, hydro-mechanical gates will be installed for the diversion tunnels, and instrumentation works will be executed to ensure operational efficiency and safety. The contract is scheduled for completion within 30 months.

The construction of the tunnels and associated infrastructure will improve the functionality and safety of the dam, supporting the region’s renewable energy and water regulation initiatives while strengthening local engineering and construction capabilities.

← All latest storiesBack to top →