Illustrative image – not actual.Patel Engineering, on 21 August 2006, bagged a contract worth Rs.318 crore from NTPC for developing the head race tunnel associated with 4x150 MW Loharinag Pala hydro electric power project in Uttarkashi district of Uttaranchal.
The project is scheduled for completion within 38 months. The project will comprise a 6m dia horse shoe shaped 13 km long concrete lined head race tunnel on the right bank of river which will be executed through three access adits using drill and blast technique.
Hindustan Construction Co, on 8 August 2006, had announced the winning of a Rs.246 crore contract for a different civil works package for the same project.
Also See:
HCC bags Rs.246 crore contract for Logarinag hydel project (09-Aug-06)
Related Links:
Project profile