Passenger operations on Noida Metro to be launched in 3-4 monthsIllustrative image – not actual.

Passenger operations on the 21 station corridor of Noida metro will be launched in three to four months.

A four coach train made its first official test run on 2 January 2018 on a section of the 29.7 km Aqua line connecting Noida and Greater Noida. Full-fledged trials along the whole corridor are likely to start by March 2018. However, even if commercial operations begin in April, commuters will have to wait till at least September to be able to access the Delhi Metro trains without having to exit the Metro corridor.

The first of the 19 Chinese-made rakes that will run on the Aqua line was flagged off for the official test run from Depot, the terminal station in Greater Noida.

Electrical and mechanical work for the corridor is 70 percent complete. Track laying and system work is in progress. Ninety percent of the track has been laid and signalling work is 65 percent complete.

Structural work on all 21 stations is also complete and finishing work is being carried out.

The Aqua line will be integrated with the extension of the Blue line via an interchange at Sector 52 of the Noida City Centre to Sector 62 Metro corridor.

In the initial phase, Noida Metro Rail Corporation (NMRC) will operate 11 trains along the corridor. The corridor will have a total of 19 train sets with 76 coaches.