The Standing Committee on Petroleum and Natural Gas has demanded review of all contracts of Reliance Industries’ (RIL) KG-D6 block.

The panel has asked government to impose stringent provisions for failure to adhere to committed work programme like drilling of wells. The drop in output at Dhirubhai-1 and three fields in the KG- basin block to 32.94 million cubic meters per day this month from the 54 mmcmd peak hit in March 2010, has been blamed on RIL not sticking to its commitment of putting 22 wells on production by March 2011 and, another nine by April 2012. The panel opines that there is no specific penalty stipulations in Production Sharing Contracts (PSC) in case of shortfall in achieving the production targets envisaged in either the approved field development plan (FDP) or annual work programme and Budget.

According to the approved development plan, output should have reached 61.88 mmcmd this month. Associated gas production from the MA oil field in the same licence area was 6.86 mmcmd, for a combined total of 39.8 mmcmd, versus the expected 70.39 mmcmd. RIL has so far drilled 22 wells on D1&D3 but has not put four wells on production due to insignificant volumes. Of the 18 wells connected to production system, four had been shut due high water cut. One well on MA oilfield has also been shut down.

Also See:

Reliance Industries finalises gasoil term deal with buyers (16-December-11)

← All latest storiesBack to top →