Illustrative image – not actual.The Rs 61-crore multi-level parking project at PGIMER, Chandigarh, has reached 70 percent completion, yet remains at a standstill due to a ten-month-long deadlock over environmental clearances.
Despite being approved over a decade ago in 2015, the seven-storey structure’s progress was halted in July 2025 following a notice from the Chandigarh Pollution Control Committee (CPCC). The project, which covers 26,000 sq. mtrs. failed to secure mandatory green clearances required for large-scale constructions. Currently, the institute is in the protracted process of hiring an environmental consultant to address the legal violations of the Air and Water Pollution Control Acts. According to contractor Rishabh Sharma, while the majority of the structural work is finished, the remaining 30 percent can only be completed once work resumes. Consequently, the original 18-month timeline has been discarded; officials and the contractor now estimate that the facility—intended to house over 900 vehicles, will not be ready until 2027.
Lt Col Gurvinder Singh Bhatti, PGIMER’s Superintending Hospital Engineer, said, “We are in the process of issuing a Request for Proposal for hiring a consultant. Once an environment consultant is on board, clearance for other projects will also be sought simultaneously.”