Paradip Port selects DCI for dredging projectIllustrative image – not actual.

Paradip Port Trust has sought the Shipping Ministry's approval for the revised cost estimate of its channel deepening project from Rs.136 crore to around Rs.235 crore.

Dredging Corporation of India has been selected as the dredging contractor from five bidders in the fray. The formal appointment of DCI will be made after the cost escalation is approved.

PPT intends to deepen the draft of its proposed iron ore and coal berths from the current 12.5m to 16m, by dredging a volume of 15 million cubic metres. This will enable the proposed berths to handle super-Panmax vessels (1,20,000 dwt and higher). The two berths will be developed on BOT basis with the project report already lying with the Public Private Partnership Appraisal Committee (PPP-AC). The two berths will cost Rs.800 crore and Rs.600 crore, respectively.

It may be mentioned that Paradip Port Trust had first floated a tender on 16 December 2005. However, this tender was cancelled and a fresh call was made on 25 July 2006. Dredging Corporation of India had not bid for the earlier tender, but has done so in the subsequent floatation.

In another development, PPT is awaiting the final report on the additional berths project at the west dock complex. RITES, the project consultant, is expected to submit the report by December 2006. The new berths will aim to add 16 million tpa of handling capacity. The new berths will be developed in public-private partnership.

Also See:

Paradip Port aims at 100 mt capacity by 2012 (18-Jul-06)

Five bidders for Paradip channel deepening project (13-Jul-06)

Related Links:
Project profile

← All latest storiesBack to top →