Illustrative image – not actual.Indian Oil Corporation is targeting to complete its Rs.1,178 crore Paradip-Haldia crude pipeline within by June-July 2007.
The proposed project - including single-point mooring and storage facility at sea port at Paradip in Orissa - had run into rough weather following a series of problems involving project design, environmental clearance and differences with the Iranian contractor deployed to complete the SPM and the connecting offshore pipeline.
It is learnt that, to hasten the process, the company recently replaced the SPM project contractor - Iranian Offshore Engineering and Construction Company (IOEC) - with Oil and Gas Engineering Systems of Australia.
The project will reduce the transportation cost of crude to both Haldia and Barauni refineries in West Bengal and Bihar respectively.