Indian Oil Corporation's Paradip-Haldia crude pipeline is expected to become operational and begin to transport crude to Haldia and Barauni refineries by January 2008.

Though the proposed 330 km long pipeline was ready in early 2007, work on single point mooring (SPM) facility at Paradip was stalled owing to issues ranging from technical problems to replacement of the contractor. The pipeline project was also delayed due to the time-consuming process of securing environmental clearances for passing through the forests of Orissa, the estuaries of a number of rivers, including the Mahanadi on the coasts, posed technological challenges.