The Pappinissery-Pilathara road upgradation project will be inaugurated by mid- September 2018.
The 21 km road has been upgraded to international standards under Phase-II works of the Kerala State Transport Project (KSTP). The upgraded two-lane road has a 10 mtr wide carriageway, including 1.5 mtr wide paved shoulders.
All the civil works except road marking will be completed by 5 September 2018.
The road upgrade project under the KSTP Kannur Division was conceived in 2013. Originally the project was to be completed by 2015. However, it got delayed and the deadline got extended twice.
The estimated cost of the project is Rs 114 crore.