Gold miner PanTerra Gold has restarted its processing plant at the Las Lagunas project in the Dominican Republic

During November last year, the miner halved production at Las Lagunas after experiencing mechanical issues with the ball mill. A replacement ball mill motor has been installed, with the mill handling the grind of coarser refractory tailings from the Pueblo Viejo mine, currently being fed into the plant. With the regrind section of the process plant is operating to design capacity, the technical team can concentrate on fine-tuning the three other circuits to optimise gold and silver recoveries.

Source: Miningweekly.com