Panel submits report for Ring Road projectIllustrative image – not actual.

A three member settlement committee formed to resolve the ring road dispute has submitted its report to state government. The long pending project is on track as the final hurdle to hand over the project to National Highways Authority of India (NHAI) was cleared.

 

The companies and Jaipur Development Authority (JDA) will accept the recommendations. The report will be tabled in the empowered committee in a week’s time. The committee has approved claims of Rs 200 crore as against Rs 566 crore submitted by the company. JDA was given approval worth Rs 10 crore as against Rs 180 crore.

A foreclosure agreement will be signed after both parties give their approval on the recommendations of the report. The state government will sign a memorandum of understanding with NHAI only after receiving the consent from both the parties. NHAI will pay the liability of Rs 221 crore to banks which was taken by Sanjose Supreme as loan to construct the 47 km ring road.

The highway authority will also provide Rs 350 crore to JDA in 10 years for commercial operation. This is as per the conditions of the agreement, which will be signed between NHAI and JDA. The project is estimated to be completed in 15 months. The final bidder for the ring road project was selected in June 2011.

The awarded firm was expected to complete the work in 24 months. However, the project was stalled due to infighting in the company. The state government has now set a deadline of August 2018 for completion of the project.