Illustrative image – not actual.Pakka has detailed out the scope of its Jagriti Project, with the ongoing capital expenditure programme, located at the company’s Ayodhya facility, revised to Rs 744 crore.
This increase from previous estimates is attributed to technical design changes, foreign exchange fluctuations, and a four-month time overrun. The project is a composite initiative focusing on capacity expansion and backward integration. Key components include the installation of a new 100 TPD paper machine (PM-4), the upgradation of PM-3 (increasing capacity from 70 to 80 TPD), and the modernization of the pulp mill from 130 to 180 TPD. Additionally, the plan covers a 15 MW captive power plant, a chemical recovery system, and an upgraded effluent treatment plant.
The investment is structured in three phases, with Phase I upgrades largely complete. Phase II, involving the PM-4 commissioning, is targeted for December 2026, while full commercial operations are slated for 01 January, 2027. Funding is supported by a Rs 129.91 crore preferential issue.