Illustrative image – not actual.The Ghazi
Barotha hydropower project, undertaken with the objective of meeting power
demand in Pakistan is expected to be completed by 31 July 2003, against its
original deadline of December 2002. The project is being built on the left bank
of Indus River in Swabi, Haripur and Attock districts.
The total project cost is Pakistani Rs.89.8 billion. Till date, Pk Rs79.7
billion has been spent involving construction of a barrage 7km downstream
Tarbela Dam on Indus River, a 52km-long power channel with a capacity of 1,600
cusecs and a 1,450 MW power house.
Work on the project had commenced in December 1995 and has been funded by
international agencies including multi-lateral agencies like World Bank and the
Asian Development Bank. The power thereby generated, will be transmitted
through national grid systems.