Pakal Dul hydel project in Jammu and Kashmir achieves first milestoneIllustrative image – not actual.

The Pakal Dul hydel project in Jammu and Kashmir with a capacity of 1,000 MW and being executed by the Chenab Valley Power Projects has achieved its first milestone.

The project has completed the construction of the main access tunnel of the powerhouse ahead of schedule on 18 December 2018. The foundation stone for the project was laid by Prime Minister Narendra Modi on 19 May 2018. The project is part of the Prime Minister’s Development Package for the state and is scheduled to be completed in five-and-a-half years.

An adit to the powerhouse was also completed on 13 December 2018. The dam works have been taken up. Pakal Dul hydel project is the biggest hydroelectric power project under construction in Jammu and Kashmir and is also the first storage scheme in the state.