Illustrative image – not actual.Chennai Container Terminal (CCT), a subsidiary of P&O Ports, is updating the box terminal at Chennai port, which it acquired from the Chennai Port Trust (ChPT)in November 2001. The company proposes to invest around Rs.290 crore in this project.
As part of the modernisation project, CCT has
constructed well-marked pathways for trucks and tractor trailers with
signboards, designated pedestrian walkways, compartmentalised and code-numbered
stack yards and separate, areas for stuffing and de-stuffing of partly-filled
containers. It has also set up computerised operations. These efforts have led
to faster container movement with 18-22 moves per hour and zero waiting time
for ships that call on the terminal.
According to CCT’s CEO, Ganesh Raj, the company plans
to build a container terminal with efficient cargo handling systems,
information technology-driven port management systems and increased safety and
environmental procedures. This would require a thorough refurbishment and
strengthening of the wharf, construction of a new operations centre and
amenities, making better container yard pavements, bringing in new quay cranes
(QC) and rubber tyre mounted gantry cranes (RTGs) and using the tools of
information technology (IT) with an investment of US$ 59.38 million (Rs.290
crore).
Accordingly, CCT has already deployed IT
infrastructure worth US$ 2.6 million (approx. Rs.12.48 crore) and placed orders
worth US$ 28 million (approx. Rs.134.4 crore) with Noell Crane Systems GmbH for
4 super post panamax quay cranes (QC) and 10 RTGs. Five of the RTGs would be
operational in September 2002 and the other 5 in November 2002, while 2 of the
QCs would be commissioned in January 2003 and the other 2 in April. The
existing 4 QCs, taken over from the ChPT, is in operation. Two of them would be
de-commissioned when the new ones arrive.