The construction work on the carshed at Aarey, which would serve as the base for maintaining Metro coaches for Mumbai Metro Line-3, is nearing its end with 95 percent work completed. The 33.5-km-long Metro-3 which connects Colaba with Seepz via Bandra Kurla Complex is fully underground. The Aarey depot is coming up on a 25-hectare land parcel. The main depot will have the capacity to stable 30 rakes of eight cars.
The depot, with a total expenditure of Rs 328 crore, has stabling lines, workshop and maintenance building, operational control centre (OCC), access control building, auxiliary substation building, underground water tank, among others. Mumbai Metro Rail Corporation (MMRC), the executing agency for the Metro project took a review of the work along with other officials. Phase-1 (BKC to Aarey) operations will be managed from Aarey’s main monitoring centre along with the back up control centre (BCC) at Bandra Kurla Complex (BKC).
The work on the depot began in September 2017, but in, 2019, the then Chief Minister Uddhav Thackeray had stayed the work. Chief Minister Eknath Shinde’s government on July 1, 2022 commenced the work in Aarey.
The initial proposed deadline of BKC-Aarey Phase-1 was December 2023 which has now been postponed to April 2024.